— CASE STUDY · TÖRÖKBÁLINT
Outdoor Pool, Törökbálint
A premium outdoor pool in 4 weeks: structural work, surface finishing and tiling from a single contractor, delivered by FER-TEX BAU Construction.
4 weeks
CONSTRUCTION
TIME
5.0 ★
GOOGLE
CLIENT RATING
8
SERVICES
ONE TEAM
A-Z
FROM STRUCTURE
TO TILING
THE PROJECT
Complete construction of a premium outdoor pool
Pool construction, structural work and tiling from a single contractor
In Törökbálint, FER-TEX BAU Kft. delivered the structural and construction works for a premium outdoor pool project. The goal was to create a durable, attractive and technically flawless outdoor pool and wellness area.
Our team carried out the structural construction of the pool, the related surface finishing work and the tiling of the pool area and its surroundings. Throughout the work, we paid particular attention to precise execution, technical solutions that ensure a long service life, and a premium finish.
During the project, many technical details were finalised through on-site consultation and our professional recommendations. For our client, the added value lay not only in the construction itself, but also in the expert support behind every decision.
Project details
LOCATION
Törökbálint, Hungary
PROJECT TYPE
Outdoor pool construction
CONTRACTOR
FER-TEX BAU Kft.
SPECIALIST PARTNER
Dinesz-Medence Kft.
CONSTRUCTION TIME
4 weeks
CLIENT RATING
★★★★★ 5.0 (Google)

OUR SCOPE
What FER-TEX BAU Construction delivered
We managed the pool build from structure to tiling, in close coordination with our specialist partner and on schedule.
-
Pool structural construction
-
Monolithic concrete and related structural work
-
Surface finishing
-
Pool surround construction
-
Tiling
-
Technical coordination
-
Additional and variation works
-
Quality control and on-site project management
SPECIALIST COLLABORATION
Coordinated delivery
with Dinesz-Medence
The project was delivered in collaboration with Dinesz-Medence. Our partner was responsible for the pool plant and filtration systems, the electrical work, the pool liner installation and the technology systems required for operation.
By combining the building expertise of FER-TEX BAU Construction with the pool technology know-how of Dinesz-Medence, the project was delivered as a well-coordinated, high-quality pool build.




THE RESULT
A durable, premium wellness space
The finished pool combines durability, modern engineering and a refined look. It shows that, as a pool contractor, we deliver structural, surface finishing and tiling work to a professional standard.
WHY IT WORKED
-
Structural work completed on schedule
-
High-quality tiling
-
Transparent, fair project management
-
Flexible technical support on site
-
Well-coordinated collaboration between trades
-
5-star client rating
-
A premium outdoor wellness area

CLIENT REVIEW
★★★★★ 5.0 Google rating
“They built our pool in 4 weeks. We agreed on a fair price, and they kept to that agreement all the way through. The work was accurate and precise, and it was finished within the deadline. As there was no fully detailed technical design, we relied on the team’s professional advice on several occasions, and thanks to that the end result is not only impressive but technically excellent as well.
Throughout the build, we experienced a fair and helpful attitude. The handling and pricing of additional work stayed transparent every time, and not once did we feel we were being charged unjustified extra costs. The whole project ran without any conflict, which is rare on a build like this.
Based on our earlier projects together as well, I can wholeheartedly recommend the FER-TEX BAU team to anyone looking for a reliable, precise and highly skilled contractor.”
György Albrecht
CLIENT · GOOGLE REVIEW
HOW IT WAS BUILT
From setting out to a finished pool in 4 weeks
Setting out, excavation and base slab concreting, formwork block walls and ring beam, surface finishing and, finally, tiling the pool area: this is how the Törökbálint outdoor pool was built. Click the images to enlarge.